When the intervention job starts Jan. of 2028, and we have 10 days of pre-shut in period, that means that the pre-shut-in starts in end of 2027?

Modified on Wed, 5 Mar, 2025 at 12:39 PM

Yes, this is correct, the pre-shut in will then start during the last 10 days of 2027.