Yes, There is a solution in pForecast that allows you to avoid losing the volume. To maintain the volume produced for a well, the production profile used for that well must be defined as ‘volume-based’. This way, the total planned production is preserved by shifting the profile in time in case of any downtime factors or similar issues that prevent the planned production.